Construction of a new conveyor for the SFPPN, Sept-Îles Construction of a new conveyor for the SFPPN, Sept-Îles Construction d’un nouveau convoyeur pour la SFFPN, Sept-Îles

The project consisted in adding a new conveyor measuring 800 m long, with a capacity of 8,000 metric tons per hour, by connecting the current SFPPN facilities to the boat loading facilities of the Port of Sept-Îles. The project also included the modification of the existing SFPPN transfer tower and the addition of a transfer tower at the Port of Sept-Îles.

Client’s name
Société ferroviaire et portuaire de Pointe-Noire (SFFPN)
Total cost of the project
$17,5M
Project delivery methods
Engineering-Procurement-Construction (EPC)
Région
Sept-Îles, Pointe Noire

 

Nature of the services

  • Simultaneous engineering and construction with an integrated design approach
  • Preliminary and final plan and specification designs for the overall work
  • Procurement and contract management
  • General contracting and construction management
  • Monitoring services
  • Quality control and assurance
    Inspection during the construction phase
    Environmental monitoring
  • Commissioning

Quai Multiusager, Port de Sept-Iles Construction d’un nouveau convoyeur pour la SFFPN, Sept-Îles

Specificities of the project

  • New 800 m conveyor and its foundations
  • Modification of the structure of the existing towers
  • New divider
  • Addition of an electrical room

Quai Multiusager, Port de Sept-Iles Construction d’un nouveau convoyeur pour la SFFPN, Sept-Îles

Similar projects

Construction of the Alouette university pavilion, Sept-Îles Construction Pavillon universitaire Alouette-Sept-Îles

Redevelopment of the Sturgeon Falls hydroelectric power plant, Ontario


Construction of a new terminal for Consolidated Thompson, Sept-Îles


Construction of the Quai des Croisières at the Port of Sept-Îles