The project consists in the construction of a new station in Schefferville. The new building is designed to allow clients to access the train and includes a ticket booth, waiting rooms, bathrooms, technical rooms, offices, a baggage processing area and a carrousel. The building was transported in sections by train to reduce site work.
Client’s name Tshiuetin Rail Transportation |
Total cost of the project $2,6M |
Project delivery methods Engineering-Procurement-Construction (EPC) |
Region Schefferville |
Nature of the services
- Preliminary and final plan and specification designs for the overall work
- Procurement and contract management in a remote area
- Procurement strategy to maximize local benefits
- General contracting and work management
- Monitoring services
- Commissioning
− | Quality control and assurance |
− | Inspection during the construction phase |
− | Environmental monitoring |
Specificities of the project
- Prefabricated building transported on the railway
- Side track on the railway
- Construction schedule spanning over 3 years to adapt to the grants received by the client